Capital Projects and COVID-19

Date
Image
covid-19_capital_costs_web.jpg

Last updated: May 14, 2020

In light of the ongoing COVID-19 pandemic and the essential services regulation currently in place throughout the Province of Ontario, the Municipality of Middlesex Centre has re-assessed its capital projects planned for 2020.

The municipality is delaying some of its planned capital projects and is only moving forward with projects that:

  • Address a safety issue
  • Can be done with minimal risk to workers and the public
  • Impact the municipality’s ability to provide service
  • Are already underway (or in some cases were completed prior to COVID-19)
  • Would cause increased costs by delay (construction, maintenance)

The municipality’s decision to proceed with some critical projects was made in consultation with the OPP, Ministry of Labour, industry representatives and legal counsel. There will be strict protocols in place on worksites to ensure all public health recommendations are followed.
 

Which projects are moving forward?

Public Works and Engineering - Stormwater

  • Meadowcreek Storm Sewer Upgrade
  • Millcreek Lane
  • Settlement Community Stormwater Masterplan

Public Works and Engineering – Transportation/Roads

  • 10191 Longwoods Road
  • Old River Road (Glendon Dr to Pulham Rd) - Construction
  • Martin Road Reconstruction (Wellington Street to Harris Road) 
  • Poplar Hill Rd (Charlton Dr to Greystead Dr) - Construction
  • Gravel Pit Entrance Road Way- Construction
  • Vision Zero & Traffic Signage (Traffic Calming)
  • Hot Mix Resurfacing Program
  • Garden Avenue / Wellington Street W STM Sewer Upgrade
  • Willow Ridge Road - Road, Pathway & Park Drainage Improvement
  • Medway Rd (Denfield Rd to Vanneck Road)
  • Vehicle replacement (4)

Public Works and Engineering – Water and Wastewater

  • Komoka WWT - Rotork Valve Replacement
  • Sewage Pump Station #4 - Installation of new sewage pumps 
  • Kilworth West Sanitary Sewer Connection
  • Evaluation of wastewater treatment plant and tertiary filters 
  • Ilderton Wastewater Treatment Facility
  • Arva WWTF - New Facility
  • Water Supply Interconnection Phase 2, Delaware
  • Ilderton Wastewater Collection System Inspection 
  • Servicing of Tunks Lane (Water and Wastewater)
  • Komoka Wastewater Collection System Inspection 
  • Elevated Tank Inspection (Sludge Storage & Equalization Tanks)
  • Wastewater Collection System Flushing and Cleaning 
  • Water main replacement & twinning, Arva
  • Facility Condition Assessment
  • Reservoir Cleaning & Inspections

Community Services

  • Wellness Centre Capital Projects: Floor Scrubber, Cooling Tower Catwalk
  • Ilderton Arena Capital Project: Desiccant Dehumidifier, Legislated Refrigeration System
  • Changes, Ice Resurfacer
  • Pavilion Renovations, Poplar Hill Park

Fire Services

  • Replace Engine/Pumper, Ilderton Fire Station
  • Roof Repairs, Delaware Fire Station

Corporate Services

  • AV Equipment for Council Meetings

For a detailed list of capital project (high and medium priorities) that are moving forward in 2020, please see the May 13, 2020, Cost Containment Plan report to council (Item 7.6).
 

Which projects have been delayed?

Public Works and Engineering – Transportation/Roads

  • Clarke Road (Plover Mills Road to 10 Mile Road) Construction
  • Vehicle Replacement (1-backhoe)

Public Works and Engineering – Water and Wastwater

  • SCADA Replacement (2)
  • Demolishing of the Kilworth WPCP
  • Vehicle/Motive Equipment Replacement (3) 

Community Services:

  • Komoka Community Centre: Replace HVAC Units 1&2
  • Ilderton Arena: Lobby Seating
  • Wellness Centre: Replace Meeting Room Furniture
  • Weldon Park: Replace Lighting
  • Byranston Prince Andrew Facility: Asbestos Remediation (note: no risk to health and safety)
  • Delaware Lions Park: Repairs to Ball Hockey Rink
  • Denfield Park: Paint Tennis Courts
  • Kilworth Optimist Park: Tridon Park Development, Dog Park
  • Trails: Little Farm/Clear Skies Trail

Corporate Services:

  • Industrial Land Purchase

Fire Services:

  • SCBA Accessories

These deferred projects represent a value of $3.7 million. For a detailed list of project that have been delayed due to COVID-19, please see the May 13, 2020, Cost Containment Plan report to council (Item 7.6).
 

Questions?

If you have any questions about capital project deferments or other cost containment measures Middlesex Centre is undertaking in response to COVID-19, please contact Tiffany Farrell, Director of Corporate Services.