Notice: Vanneck Road Reconstruction

Date
Image
Road Closed Ahead Sign

Over the summer, the Municipality of Middlesex Centre will be undertaking reconstruction work along Vanneck Rd. Access / travel may be limited at times.

Project Details

  • Location: Vanneck Road from Ilderton Road to Sinclair Drive
  • Schedule:
    • Tentative start date – June 21, 2021
    • Estimated completion – August 13, 2021
  • Scope: Reconstruction of the existing road including: tree trimming and removal (if required); ditching; culvert replacement; guide rail replacement; granular base and sub-base regrade and compaction; asphalt surface; and pavement markings
  • Contractor: Municipality of Middlesex Centre & asphalt contractor

Questions about this project may be directed to Andrew Giesen, Transportation Manager for Middlesex Centre.